Training Materials Books Articles
Environment; Land Use
Articles

CEQA Review Of Water Supply Issues
Sign-Up to the Environment & Land Use Groups

Stephen Kostka & Marie Cooper

McCutchen, Doyle, Brown & Enersen, LLP

INDEX:
Click on a topic to see the information!
Sponsors

1. INTRODUCTION - UNRESOLVED WATER SUPPLY ISSUES

2. HISTORY OF DEALING WITH WATER SUPPLY ISSUES

   A. Early 1980s - Need to Include the Issues in the EIR

 
  B. Year 1996 - Specific Water Supply Need Not Be Identified
        for an EIR

   C. Year 1999 - EIR Predicated on a Draft General Plan Is         Fundamentally Flawed and Can't Pass CEQA Muster

    D. Year 2000 - Need to Discuss and Analyze "No Project         Alternatives"

    E. Year 2001 - EIR Must Provide Information and Analysis of         Environmental Impacts, and Not Limit Itself to The Physical         Impacts on The Environment nor Ignore The Legal Right to         Take Water.

3. CONCLUSION - NO SAFE HARBOR

 

Prevent Workplace Harassment!
To receive training materials developed by a top labor firm and their fortune 500 clients
that will help your managers and employees prevent workplace harassment,
Click Here

Shop at Amazon.com

 

DISCLAIMER

1. INTRODUCTION - UNRESOLVED WATER SUPPLY ISSUES

Many CEQA practitioners look for safe harbors in which their clients are relatively protected from legal challenges. These practitioners worry not so much about what types of analyses should or should not be overturned by the courts, as they do about what analyses and conclusions are more likely to trigger lawsuits. They advise their clients to do more than CEQA requires, figuring that the extra studies and analyses will ultimately prove more economically efficient than even a successful defense of an EIR.

With respect to water supply issues, however, these practitioners may be unable to find any safe harbor. Water supply issues have received more attention from CEQA courts in recent years than virtually any other aspect of environmental review. A string of CEQA cases relating to water have established uniquely demanding standards for consideration of the environmental impacts of supplying a development project with water. The cases appear conflicting, and arguably intrude into areas previously reserved to police power and scientific discretion. The California Supreme Court has not yet weighed in, leaving headaches for many CEQA practitioners and environmental consultants.

2. HISTORY OF DEALING WITH WATER SUPPLY ISSUES


A. Early 1980s - Need to Include the Issues in the EIR

Water supply issues were first addressed in the early 1980s. In Santiago County Water Dist. v. County of Orange, 118 Cal. App. 3d 818 (1981), the County approved a sand and gravel mining operation. The EIR did not address the details of providing water. Instead, the County imposed a condition that "[p]rior to commencement of mining operations or the issuance of a sand and gravel extraction permit, the operator shall establish an adequate water supply and appurtenant system to supply the water needs of the mining operation, processing plant and reclamation irrigation."

The Court of Appeal was unimpressed. It noted:

[The EIR], instead of specifying the equipment that will be needed, merely states that "[t]he developer will furnish the District with detailed plans of works." This is not nearly enough. The construction of additional water delivery facilities is undoubtedly one of the significant environmental effects of the project. As such, a description of the necessary construction had to be included if the EIR was to serve its informational purpose.

B. 1996 - Specific Water Supply Need Not Be Identified for an EIR

Water supply issues then lay dormant for more than a decade, and were not resurrected until Stanislaus Natural Heritage Project v. County of Stanislaus, 48 Cal. App. 4th 182 (1996). Stanislaus involved a 5,000-unit destination resort and residential community. The EIR for the project acknowledged that the project would take 25 years to build out, but that water had not been assured beyond the first 5 years. The County found the water supply impacts mitigated by a measure providing that "development requiring over 1,200 acre-feet per year of water shall not be permitted unless the applicant can show to the County's satisfaction that adequate water supplies have been made available, and that environmental impacts of those sources have been studied and mitigated per CEQA requirements."

The Stanislaus court found this approach unacceptable. It held that water supply issues could not be severed from the remainder of the project and addressed at a later date in a tiered EIR. "To defer any analysis whatsoever of the impacts of supplying water to this project until after the adoption of the specific plan calling for the project to be built would appear to be putting the cart before the horse." The court described the environmental analysis that should have occurred as follows:

We are not concluding respondent must first find a source of water for the "project" before an EIR will be adequate. . . . . [T]he decision to approve the EIR of this project does require recognition that water must be supplied, that it will come from a specific source or one of several possible sources, of what the impact will be if supplied from a particular source or possible sources and if that impact is adverse how it will be addressed. While it might be argued that not building a portion of the project is the ultimate mitigation, it must be borne in mind that the EIR must address the project and assumes the project will be built.

C. Year 1999 - EIR Predicated on a Draft General Plan Is Flawed
and Can't Pass CEQA Muster

Despite Stanislaus' acknowledgment that a specific water supply need not be identified for an EIR to be adequate, many practitioners hoped they had found a safe harbor in doing more than Stanislaus required, and certainly all that Santiago required, by identifying a specific water source for every project. Those hopes were dashed a few years later in County of Amador v. El Dorado County Water Agency, 76 Cal. App. 4th 931 (1999), where the court overturned a CEQA determination precisely because the agency had identified a water source before development was approved in a new general plan.

At issue in Amador was a proposal to acquire a hydroelectric facility and use the water not only to generate electricity, but also for consumptive uses. The court overturned the project approval for failure to evaluate the growth-inducing impacts of providing 17,000 acre feet more water for consumptive uses each year. However, the language of the decision is not limited to criticism of the agency's failure to evaluate growth-inducing impacts. Instead, the court evaluated the merits of local "water policy," and evaluated whether the local health safety and welfare would be better served by determining how much water was available and then approving the amount of development that could be served by that water, or instead deciding how much development was desirable and then finding sufficient water to serve that development:

[T]he primary purpose of the water program is to provide water supplies to meet projected increased populations. These projections were contained in a draft general plan. In other words, water policy was predicated on the population forecasts of an unadopted general plan, and water projects were tailored to the needs outlined in that still-to-be finalized document. In this case, approving a water program before enacting a general plan places the proverbial cart before the horse.

The court held "only that, in this case, an EIR predicated on a draft general plan is fundamentally flawed and cannot pass CEQA muster."

CEQA practitioners attempted to reconcile Stanislaus and Amador by proposing that an EIR identify at least one concrete water source that could become available to a project, but ensuring that there was no approval of the water source until after the development project had been approved. They hoped that the teaching of Amador was only that an environmental consultant should not guess about other agencies' future development plans, even when there is a published draft plan available.

D. Year 2000 - Need to Discuss and Analyze "No Project Alternatives"

Those hopes, however, were also dashed. In Planning & Conservation League v. Department of Water Resources, 83 Cal. App. 4th 892 (2000), the court criticized a water agency for not attempting to predict the future planning actions of other agencies.

At issue in the PCL case were the Monterey Amendments to contracts governing the supply of State Water Project water. Among other things, the Monterey Amendments eliminated so-called "paper water." Paper water is water that can be made available according to the terms of existing water supply contracts but which, as a practical mater, was unlikely ever to exist. The EIR analyzed a no project alternative which concluded that the elimination of paper water would have no real consequences because the paper water had never been realistically available before.

The court did not employ the CEQA standard of review under which a court determines whether an EIR's conclusion is supported by substantial evidence. The PCL court instead determined in the first instance that there would be consequences to eliminating paper water in terms of how planning agencies throughout the state rely upon the possibility of water that exists only on paper:

What then are the environmental consequences of removing [paper water], if contractors continue to receive the same amount of water whether or not the provision is invoked? The answer is that entitlements under table A-"paper water," so called because it exists only on paper-serve as the basis for land planning decisions. Projects that are given the clearance to proceed based upon an entitlement to X acre-feet of water might not proceed if a contractor's entitlement is reduced to (X minus Y) acre-feet.

The PCL court never did explain how a water agency could do anything but speculate about what development planning agencies might approve with and without paper water decades into the future, or how a water agency could make such a projection without running afoul of Amador. Nonetheless, practitioners looking for a safe harbor hoped that all the PCL court really wanted was an extremely robust discussion and analysis of the no project alternative, so that the consequences of denying the project could be compared with the consequences of approving the project in greater detail.

E. Year 2001 - EIR Must Provide Information and Analysis of Environmental Impacts, and Not Limit Itself to The Physical Impacts on The Environment
N nor Ignore The Legal Right to Take Water.

These hopes were tempered by the next CEQA water decisions, Save Our Peninsula Committee v. Monterey County Board of Superivsors, 87 Cal. App. 4th 99 (2001). In Save Our Peninsula, the County Board of Supervisors was presented with extensive and frequently updated information about past and projected future water supply issues. The court nonetheless overturned the Board's CEQA determinations because of how the Board handled that information.

The EIR in Save Our Peninsula established there would be little, if any, physical environmental consequences from withdrawing up to 53 acre feet per year from the Carmel River aquifer, but acknowledged that local politics and circumstances - including water shortages faced by customers of a water supplier that had been taking more than 10,000 acre feet per year without legal right - raised the question whether any increase in water extractions should be considered significant. The EIR supplied the Board with substantial information regarding past water use and future water demand, and left to the Board to determine what amount of past water use should be used as the baseline against which to measure whether water demand of the project should be considered significant. The court rejected this approach. "By inviting the Board to pick from an array of numbers to determine an important aspect of the baseline environmental setting, the EIR failed to fulfill its function of providing information and analysis of environmental impacts."

The Save Our Peninsula court also criticized the EIR for limiting itself to the physical impacts on the environment, and for not including an analysis of the legal right to take water. The court indicated that the Board should have adopted a measure that had been suggested in the EIR, requiring the applicants either to provide assurance of a valid riparian claim or to secure an appropriative permit from the State Water Resources Control Board. The court did not explain how obtaining a judicial or administrative decree confirming water rights would mitigate any impacts on the environment.

3. CONCLUSION - NO SAFE HARBOR

A comparison of the CEQA analysis of water supply issues with an analysis of a more mundane issue, such as traffic, reveals how unique water supply issue are. Requiring a project applicant to identify a specific or reasonably possible source of water is no more complicated than requiring an applicant to identify access roads to its project. However, no one would even think, for example, that there was anything wrong in using a local transportation authority's projections for new arterials in assessing future cumulative traffic impacts, even if those arterials had not yet been approved in local general plans. Similarly, no would think that, before deciding whether to vacate a regional highway that was rarely used, an agency would be required to ascertain the thoughts and desires of planners and members of all local legislative bodies in the region to determine how the availability of the highway might have influenced their future planning decisions. Similarly, no one would think to question whether a developer has a legal right to allow residents to use a freeway, or to require a developer to provide assurance that CalTrans will allow residents to use state highways as a means of mitigating traffic impacts on that freeway.

The CEQA water supply cases demonstrate nothing so much as the unique role water plays in California. It is no coincidence that the CEQA cases that address water supply issues are coordinated to times of statewide and local droughts. Until the California Supreme Court determines which, if any, of these appellate court dictates really are required by CEQA, practitioners looking for a safe harbor will have to continue searching.

DISCLAIMER: This discussion is general in nature and is not intended to and does not create a lawyer/client relationship. This discussion should in no way be relied upon or construed as legal advice, particularly since most legal outcomes are highly dependent on the facts of a particular case or situation. This discussion is provided on the condition that it cannot be referred to or quoted in any legal proceeding; if this condition is unacceptable to you, immediately delete this email and do not keep a copy of it in any form. The reader or recipient is strongly urged to consult with a lawyer for legal advice on these matters. Any reliance on the discussion information by someone who has not entered into a written retainer agreement with the lawyer providing the discussion information is at the reader's or recipient's own risk.

* MCLE * MCLE * MCLE *

  1. Legal Elite Online, LLC is a State Bar of California approved provider of continuing legal education.
    Provider number: 09777
  2. To receive up to 3 hours of MCLE credit for this topic, reply to this email or send an email to: stacy@legalelite.com and include your name and bar number..
  3. To receive more participatory MCLE Credit via email, send us an email and let us know how many credits you need and what topics interest you.