Books
Q&A 
Construction
Articles

CLAIMS - SECRETS TO SUCCESS OR FAILURE:
DON'T FORGET THE DAMAGES!
Sign-Up to the Construction Group

Richard Holderness
Seyfarth, Shaw, Fairweather & Geraldson LLP

INDEX:
Click on a topic to see the information!
Sponsors

1. Introduction

2. A Contractor Must Prove Its Damages

3. When Does The Proof Begin?


DISCLAIMER

Prevent Workplace Harassment!
To receive training materials developed by a top labor firm and their fortune 500 clients
that will help your managers and employees prevent workplace harassment,
Click Here

Shop at Amazon.com

1. INTRODUCTION

Nobody talks about damages. The fight is always about liability, but the issue of damages is where a construction dispute can be won or lost. Construction disputes are about money, and the amount of money awarded or not awarded determines whether the dispute was won or lost.

A contractor can win on liability but lose the claim when it is awarded none or only a small fraction of its claimed damages. Conversely, an owner can lose on liability but win the claim if the contractor is awarded none or only a small fraction of its claimed damages.

No contractor wins a claim if the owner is found liable but pays nothing or only pennies of what the contractor is claiming. By focusing on the damages, contractors can avoid winning the battle but losing the war, and owners can win the war even after losing the battle.

2. A CONTRACTOR MUST PROVE ITS DAMAGES

A contractor cannot simply show that the owner did something wrong and that the contractor lost money on the project and then expect to be awarded the amount of its loss. (See Tele-Sentry Security, Inc., GSBCA No. 10945 (7703)-REIN, 91-2 BCA para. 23880). Instead, the contractor must prove (1) the owner did something wrong, (2) that whatever the owner did wrong caused it damage, and (3) the amount of that damage. (See James A. Boyajian, 191 Ct. Cl. 233 (1970). The contractor must prove all three. If it fails to prove either of the last two, even if it proves the owner did something wrong, its chances of winning the claim decrease dramatically.

Courts may refuse to award damages to a contractor if the contractor fails to either (1) prove that the damages were caused by the owner's wrongful act or (2) reasonably substantiate the amount of those damages. (See Joseph Pickard's Sons Co. v. United States, 209 Ct. Cl. 643 (1976)). In other words, the contractor must directly connect the owner's wrongful act to the damage it suffered and then must substantiate the amount of that damage. If the contractor fails to prove either of those two elements, it will lose because even if it proves the owner is liable, it may recover nothing or only a small fraction of what it claims.

From the owner's perspective, those two required elements give it two opportunities to break links in the contractor's chain of proof and if either link is broken, the contractor may recover little or nothing. The owner can defeat the contractor's claim by showing that the contractor failed to prove either of those two elements or by affirmatively proving that either (1) the wrongful act did not cause the claimed damage or (2) the contractor cannot substantiate the amount of that damage. Even if found liable, the owner will win if it defeats the contractor's efforts to prove (1) that the wrongful act caused the claimed damage or (2) the amount of that damage.

3. WHEN DOES THE PROOF BEGIN?

When should the contractor begin collecting its proof to show that the owner's wrongful act caused it damage and to substantiate the amount of that damage? -- At the time the wrongful act occurs.

The most reliable and accepted method of proving damages is by the contractor maintaining separate records of its costs as they are being incurred as a result of the owner's wrongful act. The contractor must also maintain records that establish the causal connection between the owner's wrongful act and the damage the act is causing.

This method of proving damages requires the contractor to have a system that allows it to immediately recognize occurrences that may lead to claims so it can begin to separately track costs attributable to that occurrence when the it first arises. Tracking costs means identifying, segregating, and the tracking costs specifically caused by the occurrence.

At the time the occurrence arises, the contractor must be able to break out, from its overall cost accounting system, those costs arising directly from the occurrence. Having a cost accounting system that can do no more than dump costs into general categories of labor, materials, and equipment, without any ability to more precisely identify categories of cost or attribute them to specific occurrences, will do a contractor little good when it is required to prove the damages caused by the occurrence.

DISCLAIMER: This discussion is general in nature and is not intended to and does not create a lawyer/client relationship. This discussion should in no way be relied upon or construed as legal advice, particularly since most legal outcomes are highly dependent on the facts of a particular case or situation. This discussion is provided on the condition that it cannot be referred to or quoted in any legal proceeding; if this condition is unacceptable to you, immediately delete this email and do not keep a copy of it in any form. The reader or recipient is strongly urged to consult with a lawyer for legal advice on these matters. Any reliance on the discussion information by someone who has not entered into a written retainer agreement with the lawyer providing the discussion information is at the reader's or recipient's own risk.

* MCLE * MCLE * MCLE *

  1. Legal Elite Online, LLC is a State Bar of California approved provider of continuing legal education.
    Provider number: 09777
  2. To receive up to 3 hours of MCLE credit for this topic, reply to this email or send an email to: stacy@legalelite.com and include your name and bar number..
  3. To receive more participatory MCLE Credit via email, send us an email and let us know how many credits you need and what topics interest you.