|
|
|
The
preceding article titled "Changes: Myth and Misadventure"
discussed the definition of a change, actual changes, cardinal
changes, and constructive changes. This article will discuss
(1) deductive changes, (2) changes as a breach of contract,
(3) the requirement for written change orders, (4) verbal
change orders, (5) whether a contractor is required to sign
change orders, and (6) the battle between waiver of rights
and reservation of rights on written change orders. This
article will rely primarily on federal law because federal
procurement law has an extremely detailed and comprehensive
changes mechanism and because almost all issues relating
to changes have arisen and been decided under federal procurement
law. Some California law also will be used. Readers should
be cautious that the issues may be decided differently in
different states. A survey of how these issues have been
decided by individual states is beyond the scope of this
article.
|
|
|
When
most people think of changes, they think of the owner
adding something to the contract or modifying some contract
requirement. Changes also can be used to deduct work from
a contract. Two primary issues arise when an owner decides
to deduct work from a contract: (1) Should the deduction
be accomplished by a change order or by a partial termination
and (2) how is the deduction priced?
A.
Change Order or Partial Termination?
Some
contracts contain a termination for conveyance clause
that allows the owner to terminate a portion of the work
for convenience. If such clause exists alongside a typical
changes clause, an owner that wants to delete work must
decide whether to use a deductive change order or a partial
termination for convenience. No standards or prerequisites
exist for choosing one method over the other, but too
broad considerations can assist in making the choice.
The
first consideration is whether the deletion is major or
minor. If the deletion is major, it probably should be
accomplished by a partial termination for convenience.
If the deletion is minor, it probably should be accomplished
by a change order. (J. W. Bateson Co. v. United States,
308 F.2d 510 (5th Cir. 1962)).
The
second consideration is whether the other work will be
substituted for the deleted work. If it will be, a change
order accomplishing both the deletion of the original
work and the addition of the substitute work probably
would be the most appropriate mechanism. If work is to
be deleted only and no other work is to be added as a
substitute, a partial termination for convenience of the
deleted work would probably be the most appropriate mechanism.
(Frederick Construction Co., ASBCA Nos. 12108, 12241,
68-1 BCA 6832; Manis Drilling, IBCA No. 2658, 93-3 BCA
25, 931). This last consideration is more in the nature
of a traditional change, and probably should not even
be considered as a "deletion" of work.
B.
Pricing A Deductive Change
Two
primary methods exist for pricing the value of deleted
work. The simplest method is where the deleted work is
a separate contract line item. In that situation, the
line item and the line item price are simply deleted.
The price of the deletion is the line item price. (See
Eugene Iovine, Inc., PSBCA 2867, 92-2 BCA 25, 013).
Although
simple, that method can be contentious if the contractor
has loaded overhead or other indirect costs into that
contract line item price. The contractor may have anticipated
that the work would be performed and paid early or perhaps
expected the quantity of work under that line item to
increase significantly. Unfortunately for the contractor,
if a line item price or separate price exists for the
deleted work, that price is the proper price to be used
for calculating the value of the deleted work. (See Oneida
Constr., Inc./David Boland, Inc., Joint Venture, ASBCA
47914, 95-1 BCAN 27, 363).
The
more difficult method for pricing deleted work is where
no separate contract line item price exists for the deleted
work and instead the deleted work is an unseverable and
integral part of the overall project. Examples might include
a deletion that would reduce the height of a wall, eliminate
a coat of paint, or decrease the depth of paving. In such
a situation, the price for the deletion is the actual
cost saved by the contractor or conversely, the cost of
the deleted work that will not be performed. The difficulty
is in determining the actual cost, with the owner and
the contractor having significantly different opinions
about the actual cost saved by the deletion.
If
a dispute arises about the actual cost of deleted work,
an owner many times will want to see the amount that the
contractor had in its bid for performing the deleted work
and for any number of reasons, the contractor will be
extremely reluctant to allow the owner to see its bid
documents. To resolve such an impasse, many contracts
now require that the documents generated by the contractor
in the process of preparing its bid be placed in escrow
and be available through escrow when a dispute arises
about the price that a contractor included in its bid
for a particular item of work.
C.
A Word of Caution to Owners About Deleting
Work
California,
New York, and perhaps other states do not allow an owner
to delete work and then have that work performed later
by another contractor. If an owner does, the original
contractor is entitled to recover its profit on the deleted
work. (See Hensler v. City of Los Angeles (1954), 124
Cal. App.2d71, 268 F.2d12). In those states, if a private
or public owner deletes work, the deletion has to be for
the benefit of the project, that is, the owner has decided
that it prefers the project without the deleted work.
The owner cannot delete the work because it wants another
contractor to perform the deleted work or it has encountered
some difficulty that may make the deleted work more expensive
and would prefer to have the deleted work performed at
a later date when the difficulty is resolved. If it does,
it may be liable to the contractor for the profit the
contractor would have made on the deleted work. (Id.)
|
3.
CHANGES AS A BREACH OF CONTRACT
|
The
earlier article about changes described an owner directed
change for work outside of the contract as a breach
of contract, which in federal terminology is a "cardinal
change." The basic test for a cardinal change is whether
it was within the contemplation of the parties when
they entered into the contact and whether the job
as modified is still the same basic job.
In
addition to one significant change that might fit
the definition of a cardinal change, a quantity of
changes so large that the quantity was not within
the contemplation of the parties when they entered
into the contract also could cumulatively constitute
a cardinal change. (See Saddler v. United States,
152 CT. CL. 557 1961); C. Norman Peterson Co. v. Container
Corp. of America, 172 Cal. App.3d 678 (1985)). Even
with a large quantity of changes, that large quantity
by itself may not be sufficient to constitute a cardinal
change. In determining whether a cardinal change occurred,
not just the quantity of changes must be considered
but also their nature and the impact that they had
on the over all project. (Id.)
|
4.
THE
REQUIREMENT FOR WRITTEN CHANGE ORDERS
|
All
construction contracts require that change orders be in
writing. A contractor that ignores that requirement does
so at its peril but paradoxically, an owner that refuses
to pay a contractor for a change solely because no written
change order was issued also does so at its peril.
A
contractor that ignores a written change order requirement
may find itself before a judge or arbitrator that believes
in the strict enforcement of contract requirements, especially
if the contract is a public contract with a state or local
public agency. Such judges and arbitrators are not swayed
by pleas that it is unfair and inequitable to have the
contractor perform work and invest its time and money
at the public agency's direction and not be paid for the
benefit it bestowed upon the public entity simply because
the formal prerequisite of a written change order was
not satisfied. Those judges and arbitrators feel it is
just as unfair and inequitable for the contractor to receive
public money without fully complying with the requirements
to receive that money.
Paradoxically,
an owner that refuses to pay for changed work solely because
no written change order was issued may find itself before
a judge or arbitrator that feels it is unfair and inequitable
to deny payment to a contractor solely because the owner
failed in its duty to issue a change order for work it
directed the contractor to perform. The safest course
for both the owner and the contractor is to comply with
all contract requirements for written change orders. The
owner can comply simply by issuing the specified written
change order. If an owner fails to issue the specified
written change order, the contractor should send repeated
written requests for the change order and provide notices
to the owner that contain all of the elements necessary
for the owner to issue a written change order.
|
|
|
Verbal
change orders or changes directed verbally can be an extremely
vexing problem for both owners and contractors, especially
on state and local public projects where adherence to
contract administrative requirements is more strictly
enforced and where issues of authority by representatives
of the public owner are more pronounced. Three primary
issues arise with verbal changes: (1) Did the person that
verbally directed the change have the authority to issue
a change, (2) was a verbal change actually directed, and
(3) what were the exact requirements of the verbal change?
Federal
contracts specifically anticipate the situation where
the federal government makes a change through some method
other than a written change order. Most federal contracts
contain a constructive change clause that define a constructive
change as: "Any written or oral . . . direction, instruction,
interpretation, or determination [other than an actual
change order] . . . that causes a change . . . [provided
the contractor gives notice] that the contractor regards
the order as a change order." (FAR 52.243-4(b) (1987)).
Although this type of constructive changes clause is rarely
found outside federal contracts, the procedure specified
by that clause is a good procedure for any contractor
faced with verbal changes or other actions by the owner
or one of its representatives that constitute changes
to the contract.
Under
that procedure, the contractor should promptly give notice
stating the date, circumstances, and source of the verbal
order and that the contractor regards the order as a change.
If possible, the contractor if possible should include
in the notice an estimate as precise as possible of the
time and cost impact of the verbal change.
|
6.
WHETHER A CONTRACTOR IS REQUIRED TO SIGN CHANGE ORDERS
|
This
is more of a practical issue than a legal issue. Owners
should never require the signature of the contractor as
a prerequisite to the effectiveness of a change order.
Such a requirement gives the contractor control of the
change order process and the veto power over changes.
The
owner wants the sole and exclusive right to make changes
to its project. It does not want to grant a contractor
a veto right over those changes. In its construction contracts,
an owner should always include the requirement that all
changes be in writing, but it should never require the
contractor's signature as a prerequisite to the effectiveness
of the change order.
The
change order should be effective upon signature by the
owner and delivery to the contractor. The contract should
allow the contractor to sign the change order if it agrees
with its terms, especially the terms about time and money,
and the contract should specify the exact effect of the
change order once signed by the contractor. However, the
owner should never give the right to the contractor to
hold the entire change process hostage by requiring the
contractor's signature to make a change order effective.
|
7.
THE BATTLE BETWEEN WAIVER OF RIGHTS AND RESERVATION OF RIGHTS
ON WRITTEN
CHANGE ORDERS
|
Owners
and contractors often have diametrically opposing views
about whether a contractor's right to impact costs should
be waived or should be reserved on written change orders.
Owners commonly prepare change orders that contain an
express waiver of a contractor's rights to any additional
costs or time other than what is allowed in the change
order. Those waivers usually require the contractor to
waive its rights to any additional delays or extensions
of time and any costs for jobsite overhead, home office
overhead, loss of productivity, or any other type of indirect
cost or impact cost. Contractors are well advised not
to sign a change order with such a broad waiver of its
rights unless it is absolutely positive that the change
order, in conjunction with other change orders and other
events on the project, will not under any circumstances
cause additional delays or generate any additional costs.
Despite sophisticated scheduling and cost accounting techniques
now available, contractors cannot always with certainty
predict the effect that a change order may have on the
project schedule or the project cost at the time the change
order is issued.
Contractors
usually want the opposite. They want a broad reservation
of rights to later claim additional time or additional
costs of any type resulting from the change order. Owners
are reluctant to allow contractors such a broad reservation
of rights because they do not want the change order payment
to be nothing more than a down payment on an endless series
of requests for additional costs and time resulting directly
or indirectly from that change order. In return for the
payment, the owners want the contractor to analyze the
changed work and tell the owner whether that work effects
the project schedule or project cost.
Owners
routinely reject change orders onto which contractors
have inserted a reservation of rights just as contractors
routinely refuse to sign change orders onto which owners
have inserted a waiver of rights.
Many
contractors recognize that an owner has a legitimate concern
about managing the time and cost of the project and has
a legitimate right to ask the contractor to inform it
of the cost and time impact of a change order. At the
same time, many owners understand that a contractor might
not be able to analyze and predict the exact impact that
a change order may have on the project without knowing
what subsequent change orders and events may impact the
project, its cost, and its critical path. Many owners
and contractors recognize that a reasonable compromise
is to allow the contractor a reasonable period of time
after the change order is signed to analyze and predict
its cost and time impact and then inform the owner. That
period will vary with the type and magnitude of the project
but it could range anywhere from one month to six months.
If the contractor does not inform the owner within the
designated period of the cost and time impact of the change
order, the contractor waives its rights to any additional
time or cost resulting from that change order.
Owners
can also use scheduling requirements to force contractors
to analyze and identify the cost and time impact of change
orders. Many contracts contain scheduling requirements
in which the contractor is required each month in monthly
schedule updates to graphically depict on the updated
schedule the impact of any changes issued in the preceding
month and to describe any delays and costs associated
with those delays in a monthly schedule narrative.
|
|
|
The
owner's right to make changes and the procedure for making
those changes are a product of the contract between the
owner and the contractor. Both the owner and the contractor
should carefully read and fully understand both the owner's
right to make changes and the procedure for making those
changes, and both should strictly adhere to the specified
procedure.
In
addition to understanding the specified contractual process
for change orders, owners and contractors should understand
the definition of a change, actual changes, constructive
changes, cardinal changes, deductive changes, changes
as a breach of contract, written change order requirements,
verbal change orders, a requirement for the contractor
to sign change orders, and the battle between a waiver
of rights and reservation of rights.
Even
if both the owner and the contractor develop a full understanding
of the contractually specified change order process, adhere
to that process, and understand the various issues relating
to changes, disputes about changes and change orders will
still be inevitable, but the number and magnitude of the
disputes will be reduced.
|
| RETURN
TO TOP |
| DISCLAIMER:
This discussion is general in nature and is not intended to and does not create
a lawyer/client relationship. This discussion should in no way be relied upon
or construed as legal advice, particularly since most legal outcomes are highly
dependent on the facts of a particular case or situation. This discussion is provided
on the condition that it cannot be referred to or quoted in any legal proceeding;
if this condition is unacceptable to you, immediately delete this email and do
not keep a copy of it in any form. The reader or recipient is strongly urged to
consult with a lawyer for legal advice on these matters. Any reliance on the discussion
information by someone who has not entered into a written retainer agreement with
the lawyer providing the discussion information is at the reader's or recipient's
own risk. |
|
* MCLE *
MCLE * MCLE *
- Legal Elite Online,
LLC is a State Bar of California approved provider of continuing legal education.
Provider number: 09777
- To receive up to 3
hours of MCLE credit for this topic, reply to this email or send an email
to: stacy@legalelite.com and include your name and bar number..
- To receive more participatory
MCLE Credit via email, send us an email and let us know how many credits
you need and what topics interest you.
|
|
|