|
1.
Introduction
|
|
The
goal of any lease transaction is to achieve a meeting of
the minds documented in reasonably sufficient detail within
that period of time necessary for each party to achieve
the economic benefit they reasonably expected. Unfortunately,
it doesn't always work out that way. The following are some
of the reasons why.
|
|
2.
The Mis-Match Game - Tenant or Landlord Build?
|
|
There
are only two (2) construction scenarios - the tenant-build
and the landlord-build, determined by which party contracts
with the general contractor. Each scenario must be matched
with the appropriate method of determining the commencement
date.
·
In the tenant-build scenario, the outside commencement
date is a fixed date (whether that date is specified [e.g.,
"April 1, 2001"] or determined by reference to another
event [e.g., "90 days after full execution and delivery
of this Lease"]).
·
In the landlord-build scenario, the outside commencement
date is the substantial completion of the improvements
by landlord.
In each
case, the commencement date may be earlier, if tenant elects
to occupy the premises for the conduct of business prior
to the outside commencement. Also, each of these outside
dates should be subject to adjustment for delay caused by
the party that is not responsible for the contracting. In
the tenant-build scenario, the outside date would be further
subject to adjustment for force majeure delay. These are
long-established industry standards for shifting the responsibility
for the economic loss resulting from delay to the appropriate
party.
The
dead giveaways that an error has been made in the negotiation
of these issues is either:
·
The association of the "substantial completion"
concept with a tenant-build, or
·
The association of the "fixed date" concept with
a landlord-build.
Although
there are rare cases in which deviation may be appropriate,
deviation from these industry standards should be generally
be viewed with suspicion.
|
|
3.
Supervision Fee? What Supervision Fee?
|
|
Supervision
fees are essentially a discount from the allowance that
the landlord purportedly uses to cover the costs of landlord's
participation in a tenant-build scenario. The fees may be
defined as a fixed amount or a percentage of something.
That something may be the allowance, or all or certain categories
of the costs of performing the improvements, and may include
both costs paid by landlord or tenant. There is no right
or wrong in the why or how of computing these fees, there
is only at issue the amount of this discount.
As such,
this is an economic/business issue that should not be left
for a tenant to first discover in the standard form of the
work letter or lease. Avoiding discussion of the fee and
how it will be determined, or "leaving it to the attorneys"
as if it is a legal issue can only breed distrust in the
prospective tenant. Distrust leads to suspicion that the
landlord is playing games or hiding the ball not only on
this, but other issues.
|
|
|
| 4.
Where's The Plan? |
|
One
landlord-build scenario is the "turnkey" build-out. In this
scenario, all of the economic terms of the lease are negotiated
based upon a defined scope of work set forth in sufficiently
detailed plans and/or specifications that become part of
the lease at execution. If the approved plans that are part
of the lease are changed by the tenant after execution resulting
in an increase in costs, then the tenant is responsible
for payment of the same.
Execution
of the lease by landlord and tenant should reflect their
knowledgeable consent to all of the economic terms, including
the cost of the improvements. This can only happen if the
sufficiently detailed plans and/or specifications are actually
available to attach to the lease at execution.
Nevertheless,
the planning process is often mistakenly ignored or delayed
by the parties while the lease is being negotiated. In order
for the process to move forward to complete a successful
lease transaction, several things have to occur while the
documentation is being addressed:
·
The landlord and tenant have to agree prior to the execution
of the lease as to how the cost of planning will be absorbed,
whether the transaction is completed or abandoned.
·
The tenant's active participation in the planning process
must be monitored by the landlord to assure that the plans
will be completed in the time that the landlord expects
to achieve the economic value assumed in the transaction.
·
The cost of the improvements reflected in the plan must
be accurately estimated (and re-estimated) so that the
economics of the transaction can be adjusted accordingly.
If the
foregoing cannot reasonably be achieved, then it is likely
that a "turnkey" scenario is inappropriate for the proposed
transaction.
|
| 5.
Let Me In! Let Me In! |
|
Contrary
to the foregoing situation, in this pitfall the tenant's
planning process and business needs are permitted to get
ahead of the negotiation of the documentation. The tenant
has a pressing business need to occupy the premises by a
specific date and focuses entirely on the planning process
to the detriment of the documentation. This may result from
the tenant having inadequate resources to address both issues
simultaneously, or a mistaken belief on the part of the
tenant that attorney's fees will be wasted if the tenant
is not first entirely satisfied that the space will work
for the tenant.
In any
event, the result is a demand by the tenant that it be allowed
to access the premises and start construction prior to the
full execution and delivery of the lease. A landlord's initial
response to this request should be: "Not by the hair of
my chinny, chin, chin!"
The
landlord's invitation to start construction is an invitation
to further procrastinate in addressing the lease documentation,
raise an unreasonable quantity or type of comments, or both.
If the landlord is inclined to accommodate such a request,
then it should not be to the detriment of landlord in completing
the negotiation of the lease. Appropriate considerations
are:
·
Limiting the extent of the construction activities to
that which will not harm landlord if the transaction is
abandoned (e.g., limiting the activity to demolition of
improvements that landlord cannot reuse in any event).
·
Indemnity and security for restoration if the transaction
is abandoned.
·
The ability to stop any early construction without cause
or penalty (including claim of landlord delay).
·
Conditioning any agreement for early access on the receipt
of all initial comments to the standard lease form with
the understanding and acknowledgement that there are no
more, and the commitment to a strict schedule for completion
of negotiations.
|
|
|
| 6.
It Is What It Is And That's All That It Is |
|
The
phrase "as-is" to a landlord means that the landlord is
not going to spend anything or assume any obligation in
regard to the improvements or conditions described as "as-is"
unless an obligation is specifically set forth in the lease.
Unfortunately, this phrase is later read by tenants to be
"as it should have been" once they discover that certain
unbudgeted items must be addressed.
Again,
there is no right or wrong as to the use of this language
- the goal is simply to achieve a meeting of the minds by
the time that the transaction must be completed, preserving
the economic expectations of each party.
For
this meeting of the minds, several things must occur:
·
The lease must define in reasonable detail the components
of the building that are intended by the landlord to be
accepted by the tenant in its "as-is" condition. In an
industrial lease scenario, it may be entirely appropriate
for the structural portions of the building to be included,
so long as that is accepted by the tenant.
·
The tenant must accurately assess the condition of any
improvement to be accepted "as-is" that the tenant plans
to reuse, both for being in good working order and condition,
and in compliance with law.
·
If improvements are not in compliance with current laws,
the tenant must consider whether these improvements will
be required by building authorities to be upgraded or
modified in connection with other intended improvements.
The
failure to address these issues as early as possible in
the negotiation process will inevitably lead to delay.
Obviously,
it is preferable for a landlord not to have to undertake
these investigations, as the result will inevitably be a
demand for the landlord to make representations and warranties
based upon the expert opinions it obtains. These representations
and warranties effectively become exceptions to the "as-is"
language that conditionally obligate the landlord to make
certain improvements. If representations and warranties
are required on behalf of the landlord , they should be
carefully drafted to be limited to actual knowledge of particular
individuals, defined improvements and laws then existing
and applicable to these improvements (if compliance with
laws is an issue). Reasonable wear and tear should be an
exception to any representation as to the condition or working
order of improvements already in place.
|
|
|
| 7.
The Turn(Key)Ing Of The Screw |
|
One
of the goals of a landlord in proposing a "turnkey" build-out
is to achieve savings in the cost of construction, and to
capitalize as much as possible on existing improvements
(assuming the lease is of second generation space). In order
to maximize this possibility, the actual cost of construction
should not be shared with the tenant, provided that the
cost is within the economic parameters assumed by the landlord
in the negotiation of the rent; and, the tenant should not
have any incentive to require more than is necessary for
the tenant to occupy the space for the conduct of its business.
Nevertheless,
it is not unusual to see the following description of landlord's
obligation in a letter of intent: "Landlord shall improve
the premises in accordance with a mutually agreeable space
plans, not to exceed $25.00 per rentable square foot." Does
this language describe a "turnkey" build-out or a landlord-build
with an allowance? It does neither, mixing the concepts
to the detriment of the landlord.
The
tenant with the knowledge that the landlord is willing to
spend $25.00/RSF has no incentive to economize by maximizing
the use of existing improvements or avoiding unnecessary
extras if it all falls within the defined "allowance." That
is when the tenant "turns the screw" to realize the savings
achieved within the defined "allowance" by insisting it
be applied against trade fixtures, furnishings, or excused
rent.
The
best way for the landlord to stay entirely within the parameters
of a classic "turnkey" is to avoid any confusion of the
"allowance" and "turnkey" scenarios by taking the following
steps:
- Avoid
disclosure of landlord's budget for improvements.
-
Agree to pay for one round of preliminary planning to
determine the extent of the tenant's requirements before
quoting a rental rate commensurate with the extent of
the improvements being requested. This is a small price
to pay up front to avoid later giving away much more in
cash savings.
- Insist
on use of landlord's architect, who will be employed by
landlord. This helps control the process in that the landlord
may discuss the budget with the architect to assist them
in limiting the planning to realistic parameters, without
disclosure of specific costs to the tenant. An architect
that always designs to the limit of the budget will not
likely continue benefit from the volume of landlord's
business.
- Only
discuss payment of excess costs with the tenant, and assist
in reworking the space to meet both the tenant's and landlord's
budget.
|
7.
Responsibility for Disabled Access Improvements
(provided
by Greg
Hurley)
|
|
Responsibility
for disabled access improvements is becoming a sticking
point in many lease negotiations. In California and several
other jurisdictions a tenant's improvement can trigger a
landlord's obligation to bring the "path of travel" to the
improved area (often from the curb or public access) into
strict compliance with new access requirements. For example
a TI that involves structural alterations, even if minor,
could require a landlord to construct new accessible parking,
new common areas, new restrooms, etc.
The
cost of the improved access the landlord must provide could
be several times the cost of the TI. While many building
departments will recognize "hardship exceptions" for landlords,
the real threat here is often delay. Often the building
officials will not approve plans or issue a C of O for a
TI until these path of travel issues are addressed.
|
|
|
| DISCLAIMER:
This discussion is general in nature and is not intended to and does not create
a lawyer/client relationship. This discussion should in no way be relied upon
or construed as legal advice, particularly since most legal outcomes are highly
dependent on the facts of a particular case or situation. This discussion is provided
on the condition that it cannot be referred to or quoted in any legal proceeding;
if this condition is unacceptable to you, immediately delete this email and do
not keep a copy of it in any form. The reader or recipient is strongly urged to
consult with a lawyer for legal advice on these matters. Any reliance on the discussion
information by someone who has not entered into a written retainer agreement with
the lawyer providing the discussion information is at the reader's or recipient's
own risk. |
|
* MCLE *
MCLE * MCLE *
- Legal Elite Online,
LLC is a State Bar of California approved provider of continuing legal education.
Provider number: 09777
- To receive up to 3
hours of MCLE credit for this topic, reply to this email or send an email
to: stacy@legalelite.com and include your name and bar number..
- To receive more participatory
MCLE Credit via email, send us an email and let us know how many credits
you need and what topics interest you.
|
|
|
|
|