|
CALIFORNIA
SUPREME COURT HOLDS THAT THEORY OF "ABANDONMENT" OF CONTRACT
DOES NOT APPLY TO PUBLIC WORKS CONTRACTS
Sign-Up
to the Construction Group
|
|
Gordon Hunt, Esq.
Hunt Ortmann, Blasco, Palffy & Rossell,
Inc., A Professional Corp.
|
|
INDEX:
Click on a topic to see the information!
|
Sponsors
|
|
1.
INTRODUCTION
2. FACTS
a.
Bidding
b. Change Orders
c. Claim for Non-Captured Change Order Costs
3.
ISSUES
4.
ANALYSIS
a.
Inconsistency with the Purpose of Competitive Bidding Statutes
b. Public Policy Concerns
c. Private Works
d. Recovery Based on "Total Cost" Measure of Damages
e. Recovery Based on "Actual Cost" Measure of Damages
5.
COURT'S DECISION
6.
CONCLUSION
|
Prevent
Workplace Harassment!
To receive training materials developed by a top labor firm
and their fortune 500 clients
that will help your managers and employees prevent workplace
harassment,
Click Here

DISCLAIMER
|
|
1.
INTRODUCTION
|
|
In the
case of Amelco
Electric v. City of Thousand Oaks (California Supreme
Court No. S091069, filed 2/4/02), the California Supreme
Court held that the theory of "abandonment" does not apply
against a public entity. The court also held that Amelco
had not presented sufficient evidence to warrant instructing
the jury on total cost damages for breach of contract. The
Supreme Court remanded the case to the Court of Appeal with
instructions to remand the case to the trial court for a
re-trial on the issue of damages.
|
|
2.
FACTS
|
|
a.
Bidding
In 1992,
the City of Thousand Oaks ("City") solicited bids
for electrical work to construct a Civic Arts Plaza. Instead
of a general contractor, the project was managed by Lehrer
McGovern Bovis, Inc. ("LMB") and the City solicited
bids from various prime contractors. It was a multi- prime
contract. The City received five electrical work bids. Amelco
was low and was awarded the contract. All five bids were
within ten percent of each other and the three lowest bids
were within three percent of each other.
b.
Change Orders
During
the two-year construction process, the City issued 1,018
sequentially numbered sketches to various contractors to
"clarify" or "change" the original contract drawings or
to respond to requests for information (RFI's). The vast
majority of the changes were to one building (the office
building) and outside lighting. Of the 1,018 sketches, 248
affected electrical work. Amelco requested 221 change orders
and the City and Amelco agreed on 32 change orders. Pursuant
to those change orders, the City paid Amelco $1,009,728.00
above the contract price ($6,158,378.00), an increase of
nearly 17%.
Amelco
claimed the project involved an unusually high number of
sketches that were difficult to work with, the scheduling
of the various contractors' work became more difficult as
a result of the changes, it was required to delay or accelerate
particular tasks and to shift workers among tasks to accommodate
work by other trades, it (Amelco) was unable to produce
documentation of instances in which its performance of a
work directive or change order was delayed or interfered
with by LMB's actions for which it was not compensated,
and that the shear number of changes made it "impossible"
to keep track of the impact any one change had on the project.
Amelco conceded it was inefficient, but assigned responsibility
for virtually all of the inefficiency to LMB.
In
May, 1993, Amelco wrote LMB concerning Work Directive 48,
Addendum No. 1, which Amelco claimed improperly shifted
engineering responsibility to Amelco. Amelco requested a
change order for $203,759.00 to hire a drafter to update
drawings, a foreman and a project engineer. LMB rejected
the request on the basis that those tasks were included
within the original contract price. Amelco did not hire
any additional personnel and signed a change order for zero
dollars and zero additional time because LMB verbally promised
Amelco that "things are going to get better". On July 29,
1994, over one year later, and two months before project
completion, Amelco requested a second change order for Work
Directive No. 48. Amelco asserted the executed change order
did not include any field productive labor impact or related
problems and that the price for this work will follow in
the near future. The opinion does not state what happened
with regard to that second change order, but it is assumed
that it was never accepted and executed.
c. Claim for Non-Captured Change Order Costs
In January,
1995, (after work had been completed), Amelco submitted
a total cost claim for $1.7 million for costs resulting
from non-captured costs of the change orders. The claim
was rejected. Amelco filed suit claiming "abandonment" and
"breach of contract". By the time of trial, Amelco's claim
was $2,224,842.00 because of the discovery of additional
costs. After a five-week trial, a jury awarded Amelco $2,134,586.00.
The Court of Appeal affirmed the award and concluded that,
as a matter of law, a public works contract can be abandoned.
The City appealed to the California Supreme Court.
|
|
3.
ISSUES
|
|
The first and primary issue the California Supreme Court
addressed was whether or not the abandonment theory of liability
applies against a public entity. The court stated that under
long-standing California law, if a public contract is declared
void, a contractor may not be paid for work performed under
that contract. Further, the court had previously ruled that
"quantum meruit" (that is reasonable value of work performed)
recovery for extra work beyond the contract requirements
was generally not allowed. The court framed the issue that
it was deciding as follows:
"The
question in this case is whether a public entity is
liable under an abandonment theory to a contractor when
it makes numerous changes to the contract work, and
these changes allegedly make it difficult and more costly
to perform the contract because of delay, interference
with the work of other trades, and other problems not
captured in the price of the executed change orders."
The
court acknowledged the leading cases in California that
had applied the "abandonment" theory, all of which had dealt
with private works of improvement. Those private works'
cases had, in general, held that where an owner imposes
upon the contractor an excessive number of changes such
that it can fairly be said that the scope of the work under
the contract has been altered and the parties have ignored
the change order process an "abandonment" of the contract
may be found allowing the contractor to recover on a total
cost basis. The court acknowledged that the United States
Federal Court of Claims has historically recognized government
breach of contract liability under the doctrine of "cardinal
change". The court distinguished the "abandonment doctrine"
from the "cardinal change doctrine" stating that those two
theories are "fundamentally different". The court noted
that under the California "abandonment" cases, the parties
ceased to follow the contract's change order process and
the final project is materially different from the project
contracted for whereupon the contractor can recover the
reasonable costs for all of its work. Turning to the Federal
"cardinal change" cases, the court noted that under the
cardinal change doctrine, the cardinal change constitutes
a material breach of contract whereupon the contractor may
recover breach of contract damages for the additional work.
|
| 4.
ANALYSIS |
|
a.
Inconsistency with the Purpose of Competitive Bidding Statutes
The
court then embarked upon its "analysis". The court started
off by concluding that the abandonment theory of liability
does not apply to public entities because such a theory
is fundamentally inconsistent with the purpose of competitive
bidding statutes. The court noted that under Public Contract
Code §20162, general law cities are required to award contracts
to the lowest responsible bidder and the Supreme Court had
previously not allowed recovery on a quantum meruit (reasonable
value) basis where there is a defect in the bidding rendering
the contract void. The court stated that if they held that
the City's numerous changes could result in the contract
being set aside in its entirety, Amelco would find itself
in no different situation and therefore should receive no
different treatment than a contractor who had performed
under a void contract. The court further stated that the
City would not have the authority to contract with Amelco
for a quantum meruit (reasonable value) payment and would
be required to rebid the project. The court stated it was
without authority to abrogate the bidding statutes and make
a new contract between the parties which the City could
not do.
What
the court was, in effect, saying is that since competitive
bidding must take place on public projects, the court could
not allow a finding that a public contract had been "abandoned"
and thereby make a new contract between the contractor and
the public body allowing recovery of the reasonable value
of the contractor's services in disregard of the contract
price. After noting that competitive bidding statutes are
for the benefit of the tax payers, the court stated the
following:
"It
is difficult, however, to ascertain how the general
public benefits by allowing a contractor to claim abandonment
of the public works contract following completion of
the work, and recovery for the reasonable value of its
work; indeed, just the opposite seems true. Permitting
such recovery would appear to unduly punish the tax-paying
public."
b. Public Policy Concerns
The
court further noted that to allow a contractor to make a
claim following completion of the work, implicates significant
public policy concerns. The court noted that under the "abandonment"
doctrine, the contractor is not required to demonstrate
at what point the contract was abandoned. The court noted
that Amelco did not determine it had a claim until November
of 1994, after the work was completed. The court noted that
under the "abandonment" doctrine, a certain number of changes
is permissible, but at some indeterminent point, the next
requested change becomes "excessive" resulting in setting
aside the competitively bid contract and thereby allowing
the contractor to recover on a quantum meruit basis from
the beginning of the project onward. As a result, the "abandonment"
theory fails to provide any meaningful guidance for public
agencies to determine whether the "line has been crossed".
As a result, public entities would not receive timely notice
of claims that would allow them to make project management,
budget or procedural adjustments during the course of construction.
Contractors would be permitted to wait until the project
was completed before giving notice of "too many" changes,
resulting in intolerable uncertainty in budgeting and financing
of public construction projects. The court further noted
that allowing contractors to recover in quantum meruit,
rather than the bid cost, would encourage contractors to
unrealistically bid low with the hope of prevailing on an
abandonment claim based on numerous changes inherent in
any large public works project.
The
court buttressed its decision by citing Public Contract
Code §7105, which provides, in part, that public works
contracts may be terminated, amended or modified only if
the termination, modification or amendment is provided for
in the contract and the compensation for amendments and
modifications shall be determined as provided for in the
contract. The court concluded that "abandonment" cannot
be considered one of the changes contemplated by Section
7105.
c. Case Law - Private Works
The
court then turned to the California cases that had allowed
the abandonment and total cost theory on private works.
The court stated they are distinguishable on the ground
that they involve private parties, not public parties.
d. Recovery Based on "Total Cost" Measure of Damages
The
court noted that the public entity would be liable for breach
of contract which requires the contractor to prove the breach
and as a result of the breach, the contractor was caused
damages. The court then discussed what was required to recover
"total costs" as a measure of damages for breach of contract.
The court stated it was not determining whether "total cost"
damages are ever appropriate in a case involving breach
of a public works contract. The court merely decided whether
the "total costs" theory of damages was properly submitted
to the jury.
The
court set forth the four elements that must be proven to
proceed on a "total cost" theory:
(1) the impracticality of proving actual losses directly;
(2) the contractor's bid was reasonable;
(3) the contractor's actual costs were reasonable, and
(4) the contractor was not responsible for the added costs.
The
court then noted that in any breach of contract case, the
contractor must prove:
(1) the contract;
(2) the contractor's performance;
(3) the public entity's breach; and
(4) damage to the contractor.
Damages
for breach of contract are those within the contemplation
of the parties when the contract was entered into or were
reasonably foreseeable at that time. Consequential damages
beyond the expectations of the parties are not recoverable.
The court noted that "total cost" is generally disfavored
as the contractor proves total costs by deducting the contract
price from the total cost of performance. The court did
confirm, however, the jury verdict method of providing damages
by proving the four elements set forth above and then modifying
the contractor's recovery for any errors in its bid or any
costs incurred because of the contractor's own inefficiencies.
e. Recovery Based on "Actual Cost" Measure of Damages
The
court concluded that the "actual cost method" is preferred
because it provides the court with documented underlying
expenses insuring that the final amount of the equitable
adjustment will, in fact, be equitable and not a windfall
for either the government or the contractor. The court noted
that under the "actual cost" measure of damages, the costs
must be tied into the owner's fault.
The
court relied on the case of Huber, Hunt & Nichols, Inc.
v. Moore (1977) 67 Cal.App.3d 278 where a total cost
claim was disallowed. The court held that the contractor,
in this case, had not met its burden of proof of the four
elements and specifically, the contractor had not proven
the fourth element, to-wit, that the City and no one else
was responsible for the additional costs. The court noted
that the contractor had failed to prove how a particular
breach caused certain damages and the contractor had conceded
it had not distinguished between inefficiencies that were
the contractor's and those that were the City's. The contractor
merely reduced its claim by 5% and the jury was asked to
assume that the remaining 95% was the fault of LMB. The
contractor did not demonstrate when any particular breach
occurred and sought to recover all costs over the life of
the project. The jury was instructed that if it found that
the City had breached or abandoned the contract, the contractor
could recover the reasonable value of work performed less
payments made by the City and less costs incurred by Amelco
which were not fairly attributable to the City.
|
| 5.
COURT'S DECISION |
|
The
court held that the jury should not have been instructed
to calculate Amelco's loss from any breach of contract under
a total cost measure of damages. By reason of the fact that
the court had held that the abandonment theory was not applicable
to public projects and that the contractor had not properly
proven a total cost claim for breach of contract, the court
therefore reversed the Judgment and remanded the case to
the District Court of Appeal with instructions to remand
the case to the trial court to re-try the issue of damages.
The court thus sustained the breach of contract finding
and required the contractor to re-try the issue of damages.
Dissenting
Opinion.
There
was a strong dissent by one justice. The dissent pointed
out that it has long been the rule in California, in other
states and in the Federal Courts that where an owner imposes
upon the contractor an excessive number of changes, such
that it can be fairly said that the scope of work under
the original contract has been altered, the law provides
a remedy, to-wit, the original contract is considered mutually
abandoned and replaced with a new contract that allows the
contractor to recover its actual costs. As noted in the
majority opinion, that theory has been upheld in private
works projects in California. It has also been the law in
the Federal Court cases and is referred to therein as "cardinal
change". Whether the theory is labeled "abandonment" or
"cardinal change", it operates as a safety valve to allow
contractors to recover their actual costs when, through
no fault of the contractor, the project goes out of control.
Until
the majority decision in this particular case, no court
had ever limited the doctrine of abandonment to contracts
with private owners. Public and private contracts are interpreted
in the same fashion. The dissent pointed out that in this
case the parties deviated from the contract's change order
process by performing changes on a "price and proceed" basis.
The dissent noted that the rule should not be different
for public works projects than private works projects. The
same events that allow contractors to recover on private
projects and federal projects occur on state public works
projects. The dissent stated there was no legal precedent
for the majority's holding.
The
dissent also noted that contractors will not "bid low" and
hope to recover on an "abandonment" theory in the event
the public agency makes numerous changes. The dissent pointed
out that no contractor would take such a risk.
The
dissent further stated that allowing the contractor to seek
reasonable value where there are excessive changes will
encourage public agencies to issue adequate plans and specifications
so that intelligent bidding can take place. Further, it
would allow contractors to recover their actual costs rather
than requiring the public entity to draw up new plans and
specifications and rebid the project to comply with the
competitive bidding statutes. The dissent pointed out that
the contractor is required to complete the project under
the abandonment theory and the owner has to pay for the
excessive changes made over the life of the project. The
dissent noted that the best support that the majority had
for its opinion was Public Contract Code §7105. The
dissent pointed out, however, that said code section deals
with "termination", "amendment" and "modification". If the
Legislature had intended it to deal with "abandonment",
it would have said so. The dissent pointed out that Public
Contract Code §7105 did not repeal the common
law rule that contractual liability of a public agency is
the same as that of a private individual. The dissent concluded
by stating:
"There
being no authority or persuasive reason to prohibit application
of the abandonment doctrine to construction contracts
with public entities, I dissent."
|
| 6.
CONCLUSION |
|
Contractors
and their attorneys had assumed, based upon the California
cases that had applied the abandonment theory in the private
sector and the numerous cases that had applied the "cardinal
change" theory in the federal sector would be equally applicable
to public works projects performed in California. This opinion
of the California Supreme Court makes it clear that contractors
may no longer proceed on an "abandonment" or "cardinal change"
theory where there have been excessive changes on a public
works project. By reason of this opinion, contractors would
be well advised to give notice every time any act or event
occurs on the project not within the control of the contractor
that impacts the contractor's time or cost of performance
and request a change order for the cost and time of that
impact. Furthermore, contractors would be well advised to
promptly start the tracking of costs applicable to each
such impact so that the contractor may proceed on an "actual
cost" basis. The contractor should seek a change order under
the appropriate provisions of the contract documents. That
request may be under the Changes Clause, the Suspension
of Work Clause, or the Changed Conditions Clause. Contractors
will be allowed to continue to proceed under a breach of
contract theory under this decision. It will be necessary
for the contractor to prove the normal elements in any breach
of contract action which are outlined above. If the contractor
proceeds on a total cost basis, it will have to prove the
four elements outlined above in order to proceed on a total
cost basis for breach of contract.
It should
be noted, however, that the Supreme Court did not overrule
the "modified total cost" method of proceeding. Under the
modified total cost theory of damages, the contractor proves
the four elements outlined above, but gives a credit to
the owner for any of the elements that the contractor is
unable to satisfy. Essentially, that typically results in
the contractor giving a credit against its total costs for
any errors that the contractor made in its bid or any excessive
excess costs that were incurred as a result of the contractor's
own inefficiencies.
Under
this California Supreme Court decision, contractors will
no longer be able to proceed on a "abandonment" theory and
should make every effort during the construction project
to give notice of any event that impacts their cost or time
of performance and seek recovery under the appropriate provisions
of the contract documents (primarily the Changes Clause).
Contractors would likewise be well advised to attempt to
maintain separate cost records attributable to each breach.
Obviously, contractors should never give notice of the claim
after the project has been completed. It is the opinion
of the author that that was one of the primary reasons for
the decision, to-wit, that the contractor did not present
its $1.7 million claim until after work had been completed.
Even though the contractor did write a couple of letters
seeking a change order for one of the directives, evidently
under the evidence as submitted at the time of trial, it
did not give notice of its overall claim in a timely fashion.
|
| DISCLAIMER:
This discussion is general in nature and is not intended to and does not create
a lawyer/client relationship. This discussion should in no way be relied upon
or construed as legal advice, particularly since most legal outcomes are highly
dependent on the facts of a particular case or situation. This discussion is provided
on the condition that it cannot be referred to or quoted in any legal proceeding;
if this condition is unacceptable to you, immediately delete this email and do
not keep a copy of it in any form. The reader or recipient is strongly urged to
consult with a lawyer for legal advice on these matters. Any reliance on the discussion
information by someone who has not entered into a written retainer agreement with
the lawyer providing the discussion information is at the reader's or recipient's
own risk. |
|
* MCLE *
MCLE * MCLE *
- Legal Elite Online,
LLC is a State Bar of California approved provider of continuing legal education.
Provider number: 09777
- To receive up to 3
hours of MCLE credit for this topic, reply to this email or send an email
to: stacy@legalelite.com and include your name and bar number..
- To receive more participatory
MCLE Credit via email, send us an email and let us know how many credits
you need and what topics interest you.
|
|
|