Training Materials Books Articles
Construction
Articles
NEGOTIATING CONSEQUENTIAL DAMAGES WAIVERS
Sign-Up to the Construction Group

Charles Sink , Esq.
Farella Braun + Martel LLP

INDEX:
Click on a topic to see the information!
Sponsors

1.  INTRODUCTION

2.  AIA's ADDITION OF WAIVER OF CONSEQUENTIAL     DAMAGES PROVISION

3.  SHOULD YOU INCLUDE A WAIVER PROVISION?

4. EXAMPLE OF PROVISIONS TAILORED TO THE     TRANSACTION

5. CONCLUSION

6. FOOTNOTE (See number in brackets within text)

DISCLAIMER


Prevent Workplace Harassment!
To receive training materials developed by a top labor firm and their fortune 500 clients
that will help your managers and employees prevent workplace harassment,
Click Here

Shop at Amazon.com

1. INTRODUCTION

Three years ago the "waiver of consequential damages" provision became a part of the American Institute of Architects revised standard form construction documents. Both the 1997 edition of the AIA standard contract between the owner and the contractor (Form A201) and its standard contract between the owner and the architect (Form B141) added the waiver provision. These contracts probably are more widely used and copied than any other construction industry agreements. Because these contracts provide for mediation and arbitration, the consequential damages waivers are more likely to be interpreted by the participants in the mediation, or by arbitrators, if the dispute is not settled during mediation.

This article offers practical advice about these waivers and suggests how they can be tailored to the particular transaction.[1]

2. AIA's ADDITION OF WAIVER OF CONSEQUENTIAL DAMAGES PROVISION

The addition of the waiver of consequential damages provision was a profound change in the AIA standard form contracts. (Another profound change in these contracts was the addition of mandatory mediation under the Construction Industry Mediation Rules of the American Arbitration Association.) When these revised form contracts were issued, the AIA explained in a news release that "by setting the stakes in a potential dispute more definitively, the contract avoids a rapidly intensifying adversarial atmosphere." Howard Goldberg, counsel to the AIA Document Committee, said of the revised AIA forms, "The mutual waiver of consequential damages provision is AIA's first attempt to interject tort reform principles in the construction industry." (See "New AIA Documents Adopt Mediation," in Punch List, Fall 1997, p.5).

The waiver can be read very broadly-covering "all consequential damages." The provision goes on to itemize the types of losses covered by the mutual waiver. Section 4.3.10 (Claims for Consequential Damages) provides:

The Contractor and Owner waive all claims against each other for all consequential damages arising out of or relating to this Contract. The mutual waiver includes:

1. damages incurred by the Owner for rental expenses, for losses of use, income, profit, financing, business and reputation, and for loss of management or employee productivity or of the services of such persons; and

2. damages incurred by the Contractor for principal office expenses including the compensation of personnel stationed there, for losses of financing, business and reputation, and for loss of profit other than anticipated profits arising directly from the Work.

This mutual waiver is applicable, without limitation, to all consequential damages due to either party's termination in accordance with Article 14 (Termination or Suspension of the Contract). Nothing contained in this Subparagraph 4.3.10 shall be deemed to preclude an award of liquidated direct damages, when applicable, in accordance with the requirements of the Contract Documents.

3. SHOULD YOU INCLUDE A WAIVER PROVISION?

When drafting construction agreements, the waiver provisions should be evaluated by counsel and client in the context of the particular project. They should consider whether the benefits of having the waiver outweigh the disadvantages. For example, an owner, facing substantial financing costs and significant lost income in the event of a delay, may conclude that having the waiver would not be appropriate. (In this case, the owner might opt instead to have an appropriate liquidated damages clause.)

If counsel and client believe it would be beneficial to include a waiver provision, they may wish to tailor it to suit their transaction. However, construction parties should be aware that the scope of the waiver provision, whether or not they alter it, might be questioned once a dispute arises. This could make the role of the mediator or arbitrator more difficult, at least until better norms are established for the type of damages that may be recovered.

4. EXAMPLE OF PROVISIONS TAILORED TO THE PARTICULAR TRANSACTION

If a construction party wants to retain the waiver and exclude all consequential damages, counsel may wish to add to the arbitration clause a provision that expressly curtails the arbitrator's ability to award consequential losses. For example, this provision might state:

The arbitrators shall have no authority to award, directly or indirectly, any form of consequential damages, as such damages have been waived by the parties to this contract.

A project owner might wish to specify additional forms of consequential damages that are excluded. A sample clause might provide:

Such prohibited damages include, but are not limited to: lost profits; home office overhead or any form of overhead not directly incurred at the project site; wage or salary increases; ripple or delay damages; loss of productivity; increase cost of funds for the project; extended capital costs; lost opportunity to work on other projects; inflation costs of labor, material, or equipment; non-availability of labor, material, or equipment due to delays; increased cost of bonding due to delay; or any other indirect loss arising from the conduct of the parties to this contract.

A contractor or design professional might wish to add the following language to the waiver provision:

Such prohibited damages include, but are not limited to: lost rent or revenue; rental payments for temporary offices; increased costs of administration or supervision; costs or delays suffered by others (unable to commence work or provide services as previously scheduled) for which a party to this contract may be liable; increased costs of borrowing funds devoted to the project; delays in selling all or part of the project upon completion; termination of agreements to lease or buy all or part of the project (whether or not suffered before completion of services or work); forfeited bonds, deposits, other monetary costs, or penalties due to delay of the project; increased taxes (federal, state, local, or international) due to delay or re-characterization of the project; lost tax credits or deductions due to delay; impairment of security; or any other indirect loss arising from the conduct of the parties to this contract.
5. CONCLUSION

Since there is no universal definition of consequential damages, it behooves the drafter of the construction agreement to eliminate, to the extent possible, any potential ambiguity in the scope of waived damages. Thus, the rationale for itemizing consequential damages is to facilitate the arbitrator's understanding of the negotiated limitations, and ensure that they are respected.

Not all parties will wish to waive their right to consequential damages. A party who harbors doubts about the ability of the other contracting party to perform the contact may wish to strike the waiver provision from the agreement and provide in the arbitration clause that "the arbitrators are authorized to award any and all forms of indirect or consequential damages."

To carry out the intent of the waiver provision, the owner, design professional and contractor must stop and consider the potential savings and the possible losses for themselves and the other parties on the project. Setting a limit on the risks being taken is a worthwhile objective, but it will only succeed if those negotiating the agreement realistically consider what could happen if the schedule is not met.

AAA mediators and arbitrators, not judges or juries, will have front-line responsibility for interpreting the terms "liquidated damage" (permitted under the AIA documents) and "consequential damage." The parties should give more rather than less guidance to these neutrals so that they can continue to meet the high expectations of the AIA and the rest of the construction community.

6. FOOTNOTE

[1] A more extensive analysis of this and related damages limitations in arbitration agreements appeared in the Construction Lawyer, Vol. 18, No. 2 (ABA Forum Committee on the Construction Industry). An analysis of all the substantive changes made in the 1997 A201 Document appears in Sink & Peterson, The A201 Deskbook: Understanding the Revised General Conditions (ABA Forum on the Construction Industry 1998).

Reprinted with permission from Punch List, August 2000

RETURN TO TOP
DISCLAIMER: This discussion is general in nature and is not intended to and does not create a lawyer/client relationship. This discussion should in no way be relied upon or construed as legal advice, particularly since most legal outcomes are highly dependent on the facts of a particular case or situation. This discussion is provided on the condition that it cannot be referred to or quoted in any legal proceeding; if this condition is unacceptable to you, immediately delete this email and do not keep a copy of it in any form. The reader or recipient is strongly urged to consult with a lawyer for legal advice on these matters. Any reliance on the discussion information by someone who has not entered into a written retainer agreement with the lawyer providing the discussion information is at the reader's or recipient's own risk.

* MCLE * MCLE * MCLE *

  1. Legal Elite Online, LLC is a State Bar of California approved provider of continuing legal education.
    Provider number: 09777
  2. To receive up to 3 hours of MCLE credit for this topic, reply to this email or send an email to: stacy@legalelite.com and include your name and bar number..
  3. To receive more participatory MCLE Credit via email, send us an email and let us know how many credits you need and what topics interest you.