|
|
| Real
Estate - Construction - CaliforniawwwwwwArticles |
|
I. BACKGROUND
|
|
For 15 years Stu Parker worked for a contracting company founded
by his father. Then the family came to a reluctant decision: Stu
should go out on his own. He had no trouble getting a contractors
license. He could easily show the requisite experience. Although
he only had a high school education, he had worked his way up from
apprentice carpenter to chief estimator and then vice president
in charge of field work. He was a little rusty on some parts of
OSHA, labor law, and the mechanics lien law, but he brushed up on
those subjects and passed the exam offered by the Contractors State
License Board with flying colors. He posted his bond (B&P C
§7071.6) and his workers compensation insurance certificate (B&P
C §7125) and became the proud possessor of a California contractors
license class B (general building contractor) (B&P C §7057).
A contractor friend offered Stu an opportunity to roof a shopping
center that was already under construction. Stu was qualified to
put the roof on, all right, and he could do it at a fair price,
but he turned down the job because his class B license wouldn’t
cover roofing unless he was also doing at least one other unrelated
trade (B&P C §7057). In order to legally take a contract for
roofing work only, Stu would have needed a C-39 (roofing) license
(Cal. C. Reg. Title 16 §832.39) and he didn’t have one.
|
|
II. STU GETS A JOB
Return
to Top
|
|
A better prospect for work was offered by Nicholas Keiko. Nick
had graduated from Purdue with a degree in engineering and an MBA.
An avid hockey fan, Nick had been romancing a group of NHL players
who needed an investment outlet for their ridiculously high salaries.
Nick would provide this outlet in the form of limited partnership
interests in a 700-unit apartment project that would be built in
one of the nearby valleys. Nick knew Stu’s dad and was looking for
a contractor.
Nick, a smart, ruthless young guy, had learned a lot about finance
and real estate but didn’t know much about construction. He decided
to put his faith and confidence in Stu. Nick optioned the land,
hired an architect, and worked out his financial projections. On
paper it was a good-looking project. The NHL players were enthusiastic.
They felt that they were doing the responsible thing: making a wise
investment.
To Nick, time was money. All the money that would pour into the
land, the plans, the permits, the construction, taxes, insurance,
marketing, and everything else would be totally unproductive until
the first rent check came in. Nick pushed the architect mercilessly
and he showed a special interest in the critical path network (scheduling
by computer) that Stu was putting together.
As recommended by the architect, Nick utilized the AIA contract
forms in setting up the construction contract with Stu’s newly formed
corporation. He agreed to pay a substantial bonus for early completion.
As far as Nick was concerned, time was of the essence.
|
|
III. THE PROJECT AND TROUBLE BEGINS
Return
to Top
|
|
Stu "hit the ground running" as Nick had urged him to
do. The project got off to a fast start as soon as permits were
issued. Stu decided to do the framing work with his own forces:
he knew how to swing a hammer and had spent quite a few years running
framing crews.
He subcontracted the concrete work to the low bidder, Patrick Mahoney
of Mahoney Concrete. This is where the trouble started. The foundations
and slabs for the apartment buildings were, of course, on the critical
path of the construction schedule and Mahoney seemed to be shorthanded.
He started to fall behind. Nick pushed him mercilessly. Known on
the jobsite as "Nick of time", Nick was dealing directly
with Patrick rather than going through the prime contractor, Stu,
as the protocol of the construction industry would have required.
Under pressure, Patrick hired a new layout man and added three
crews to expedite the form work. At the same time, he was pushing
the rod busters who were working for him under a separate subcontract.
Details on the drawings weren’t clear and it was hard to get information
from the architect. Some mistakes were made in the layout and it
took time to correct them. What with one thing and another, the
job was five weeks behind schedule.
|
|
IV. THE TAKEOVER PLAN
Return
to Top
|
|
Nick’s owner’s rep, Homer, an old-time construction man from Texas
came to believe that Stu and Patrick were just incompetent to handle
a large project and keep the job on schedule. Only he, Homer, could
save the project. He and Nick laid out a plan to do a takeover.
They would remove Stu and Patrick from the job, find a substitute
concrete contractor, negotiate a takeover of the other subcontracts,
and make Homer the overall construction czar with control of the
purse strings and progress payments. Homer, knowing that Stu was
going to be thrown off the job anyway, delayed the progress payment
that was due on January 20, citing the fact that the concrete work
was behind schedule and also quibbling about the paperwork supporting
the application for payment. Homer suddenly started rejecting mechanics
lien releases with fax signatures, white-outs, erasures, and dates
and amounts that failed to match the payment applied for (Civ. C
§3262). He had his clerks raise questions about certificates of
insurance from subcontractors and other paperwork details.
Stu frantically chased down all the releases and insurance certificates
and finally presented an application for payment that was faultless
in every detail but still Homer refused to release the check. The
morale of the subcontractors and even Stu’s own superintendent and
foremans was falling rapidly. Antagonism was building up on the
job. Patrick and Stu had done everything they possibly could but
they were hampered by lack of information on the drawings and lack
of communication from the architect.
Both Patrick and Stu were just about tapped out. For the last several
weeks Stu had focused most of his attention on releases and insurance
certificates and now it was time to start processing the application
for the February 20 payment. In an impassioned phone call Patrick
threatened to pull his crews off the job. Stu dipped into his own
bank account to make a partial progress payment in return for Patrick’s
promise to make up for lost time.
Stu was not being treated fairly. His progress payments weren’t
made. His working capital was exhausted. How could he be expected
to keep the job on schedule if he couldn’t pay his subcontractors?
He wanted to walk off the job, but he kept remembering that his
father always boasted that he had never failed to finish a job.
He began to suspect that if he didn’t walk off the job Nick would
throw him off. That would be even worse! What would his father think?
Stu had been working around the clock for more than a month. He
was tired and almost broke. He had to convince Homer to release
the January draw! They set up a meeting to have it out. Stu found
out that Nick intended to attend the meeting and was also going
to bring a lawyer. The job log showed a couple of job visitors with
cameras and video equipment. Stu considered this to be an ominous
development. He looked over the default provisions of AIA document
201 and sent copies of the contract documents and draw requests
to his lawyer.
Stu knew the ethos of the construction industry. If he performed
in a workmanlike manner on schedule and on budget with the cooperation
of the owner, the architect, the subcontractors, and the building
department he got paid. If there were problems, he worked them out.
This was something new! He couldn’t pay his bills. He’d been blown
out of the water before he had a chance to perform!
|
|
V. STU TAKES A CRASH COURSE IN CONTRACT LAW
Return
to Top
|
|
Now, with some expensive help from his lawyer, he started to review
contract law. A contract, as he knew, was a two-way street. "No
money no workee" was his motto. Translated into legal language,
this meant that an unexcused material breach of contract was an
excuse for nonperformance: in other words, if one party breached
the contract the other party had the right to stop performance.
Nick was relying on this. He said Stu breached the contract by failing
to keep to the schedule, that was a material and unexcused breach
and therefore he was excused from making progress payments. But
as the owner, Nick impliedly warranted the correctness of the drawings
and specifications. Howard Contracting, Inc. v. G.A. MacDonald
Construction Co., 71 Cal.App.4th 38, 83 Cal.Rptr.2d 590 (1998).
By now, Nick was throwing in a few other "material breaches"
such as lack of compaction, inadequate rebar, and busts in the grades
of the streets. These, though, were afterthoughts. Nick’s main thesis
was that Patrick was an incompetent concrete contractor, Stu was
responsible for the performance of the subcontractor, Stu did not
properly schedule the work and was unable to make up the time that
had been lost. Patrick, on the other hand, claimed that Homer had
refused to make promised payments, that the plans were inadequate,
and the architect was not available to answer RFI’s (requests for
information). These factors, he contended, excused his failure to
keep the job on schedule.
Stu’s lawyer contended that Nick had committed a material and unexcused
breach of contract by failing to make the January progress payment.
He contended that the quibbling about releases and certificates
of insurance was just a ruse and that the real objective was to
keep Stu working on the job as long as possible for free, and then
eject Stu from the job and carry on using Stu’s subcontractors working
for Homer as the new construction czar.
|
|
VI. MATERIAL AND UNEXCUSED BREACH
Return
to Top
|
|
Stu learned that the law gave him some options. He learned that
a material and unexcused breach (failure to make progress payment)
gave him four choices: 1) continue working, finish the contract,
and sue for the contract price (McConnell v. Merrill Lynch, Pierce,
Fenner & Smith, Inc., 105 Cal.App.3d 946, 164 Cal.Rptr.
751 (1980)); 2) stop the work but keep the contract alive, remaining
ready willing and able to continue with the project when the progress
payment had been made (B.L. Metcalf General Contractor, Inc.
v. Earl Erne, Inc., 212 Cal.App.2d 689, 28 Cal.Rptr. 382 (1963));
3) terminate performance and sue for money due under the contract
plus profits that he could have earned if allowed to finish the
project. If withholding the progress payment was wrongful Stu could
collect a 2% per month penalty and attorneys fees (Civ. C §3260.1).
(McConnell v. Merrill Lynch, Pierce, Fenner & Smith, Inc.,
105 Cal.App.3d 946, 164 Cal.Rptr. 751 (1980)); and 4) rescind the
contract (B.L. Metcalf General Contractor, Inc. v. Earl Erne,
Inc., 212 Cal.App.2d 689, 28 Cal.Rptr. 382 (1963); United
States for the use of Building Rentals Corp. v. Western Casualty
& Surety Co., 498 F.2d 335 (1974); Gray v. Bekins,
186 Cal. 389, 199 P. 767 (1921)).
Whether to rescind, he learned, was a fateful decision. When a
contract is rescinded the law treats it as though it had never existed
and tries to put the parties back in the position that they occupied
before the contract was signed. Normally this meant that the owner
had to give back the consideration for the contract, but that was
impossible. The streets, curbs, gutters, and foundations were embedded
in the ground. Therefore, the owner would have to pay the contractor
the reasonable value of the contractor’s performance. Stu was surprised
to learn that rescission, if it worked, could turn a losing contract
into a winner, because, under a theory called "restitution"
the contractor was entitled to reasonable value of the performance
even if that was more than the contract price. Boomer v. Muir,
24 P.2d 570 (1933).
|
|
VII. THE PARTIES MEET
Return
to Top
|
|
Then came the meeting in Nick’s office. After the usual pleasantries,
Nick handed Stu a one-page document: a notice of default that ordered
Stu to remove his workers and supervision from the jobsite and leave
the materials and equipment to be taken over and accounted for by
Homer and utilized in the completion of the project. Black v.
City of Santa Monica, 13 Cal.App.2d 4, 56 P.2d 256 (1936). The
lawyers on both sides made their mouthpiece statements using language
that Stu could barely understand. They walked out of the meeting
crestfallen and smoldering with anger and a fierce desire for revenge.
Stu had never been subjected to anything like this. Never would
he be able to say he always finished every job!
Stu did something he never had to do before: he recorded a mechanics
lien and gave a stop notice to the construction lender. Stu started
getting legal bills monthly and paying out big money. He sued. Nick
counter sued. It was a race to the courthouse! Winning this lawsuit
had become the most important thing in Stu’s life. He’d been throwed
off a job! No matter what the cost, he had to prove it was not his
fault and he had to prove it in court.
As he got farther and farther into studying the law, he realized
that it was good thing he had not walked off the job. Then he would
have to prove that his action was justified by a material and unexcused
breach of contract. Whitney Investment Co. v. Westview Development
Co., 273 Cal.App.2d 594, 78 Cal.Rptr. 302 (1969). Since Nick
had elected to throw Stu off the job, Nick would have the burden
of trying to prove legal justification for that action – in other
words, that Stu had committed a material and unexcused breach of
contract. Under the circumstances, was the fact that the concrete
work was a few weeks behind schedule a material breach, and if it
was material, wasn’t it excused by the inadequate plans and the
architect’s slow responses to RFI’s?
In his heart, Stu knew that he was right. Whether a judge and jury
would agree, only time would tell.
|
|
|
|
YADDA, YADDA, YADDA
1. For more information go to http://www.legalelite.com/index.htm
2. If you need help or have a comment, please E-mail us at
questions@legalelite.com.
|
|
* MCLE * MCLE * MCLE *
*PROVIDER & SPONSOR: Legal Elite Online,
LLC
Provider has been approved by the State Bar of California as a continuing
legal education provider.
*MCLE INFO: click
here.
|
| DISCLAIMER:
This discussion is general in nature and is not intended to and does not create
a lawyer/client relationship. This discussion should in no way be relied upon
or construed as legal advice, particularly since most legal outcomes are highly
dependent on the facts of a particular case or situation. This discussion is provided
on the condition that it cannot be referred to or quoted in any legal proceeding;
if this condition is unacceptable to you, immediately delete this email and do
not keep a copy of it in any form. The reader or recipient is strongly urged to
consult with a lawyer for legal advice on these matters. Any reliance on the discussion
information by someone who has not entered into a written retainer agreement with
the lawyer providing the discussion information is at the reader's or recipient's
own risk. |
|